Oct 242016
 

Construction Update as of 11/20/16. This week, the contractor expects to build the forms for, install reinforcing, and cast the footings for the Addition; install the new electrical main distribution panel. In the following week of Nov. 28th we should see construction of the forms and reinforcing for the foundation walls at the Addition, and excavation for and installation of the new water and fire protection lines to the street.